Proposed 2 x 700 MW Coal Fired Power Plant at Kuala Lukut, Mukim Jimah, Negeri Sembilan-Subcontract Works for Construction Completion and Maintenance of the Cooling Water Intake Channel
Completion Date: January 2008
Client/Main Contractor: Taisei Corporation / Wibawa Works Sdn. Bhd.

Scope of Work:
  • Installation of sand key 250,000 m³.
  • Laying of filter rock and armour rock 200,000 tonne.
  • Laying of rock core 120,000 tonne.
  • Laying of under-sea geotextile blanket total 75,000 m².
Completed Rock Mount
Completed Rock Mount
Aerial view of Jimah under construction
Aerial view of Jimah under construction
Installation of rock bedding
Installation of rock bedding
Installation of geotextile
Installation of geotextile